PC Meeting with Nottinghamshire County Council at the Traffic Lights
/in News /by ClerkREPORT ON A MEETING OF RANSKILL PARISH COUNCIL WITH VIA EAST MIDLANDS, MAIN CONTRACTOR TO NOTTINGHAMSHIRE COUNTY COUNCIL HIGHWAYS
October 2026
Present:-
County Councillor
VIA EM: Assistant District Manager
VIA EM: Signals Design Manager
Parish Councillors: 3
Three issues were discussed:-
- Traffic Lights Sequence
VIA were able to witness problems with vehicles being stranded in the middle of the crossroads as the lights changed. Several vehicles were observed going through the lights on red. HGVs and farm vehicles were seen turning at the lights slowly, holding up other traffic and causing issues as the lights changed again, leaving traffic stalled as the lights changed.
VIA informed the PC that the lights were timed in accordance with national standards but realised that in our case this needed changing. This mainly due to lack of visibility as the pub and shop buildings were close to the road. VIA seemed to accept that a better option would be a four way light sequence, even though traffic would have to wait longer in a holding pattern, but would be safer. It would also increase compliance with lights on red.
Councillors felt that this could be the preferred option, rather than simply increasing the time sequences to give a longer period on green.
Our C. Cllr will progress on a regular basis to ensure the project gains funding.
- Parking at the top of Station Road
VIA observed the issue and obstructions caused by illegal parking. The officer needs better evidence to progress and asked for evidence gathering. The Clerk will arrange for photographic evidence, which will be submitted in the coming weeks.
- Blyth Road
VIA visited the site of the sharp bend on Blyth Road and met the residents of Thorn Cottage. The warning signs placed at each end of Blyth Road, unsuitable for HGVs, seems to have reduced the volume of heavy trucks. Nevertheless, there is still a significant volume of heavy vehicles, including farm traffic which cause many near misses on this narrow country road. The officer has now seen the issue and will report to their traffic planners to try to find a more intelligent solution.
As a follow up to our meeting the Signals Design Manager has issued the following note: –
I have now run through the performance modelling of the traffic signals to test the effects of changing the method of operation at the junction to separate out some, or all, of the traffic movements to try and address the issues you have here.
As we discussed, separating out the traffic movements adds extra stages and lost time into the junction operation which will affect queues and delays at the junction. The signal cycle time will increase to accommodate the additional stages increasing waiting times, and the version with all four approaches running separately will add the greatest amount of delay. By way of example, the average vehicle delay time and queue lengths on the Great North Road north approach in the AM peak are predicted to increase as follows: –
| Option | Average delay per vehicle | Mean queue length |
| Existing arrangement | 24 seconds | 4 vehicles |
| Station Rd/Blyth Rd separate | 34 seconds | 6 vehicles |
| All arms separate | 91 seconds | 11 vehicles |
The benefits of any scheme to alter the staging at the junction will have to be balanced against the cost of additional delays resulting from these changes
In the meantime, I have asked for the clearance periods between the end of each traffic stage to be increased by 2 seconds from the current 8 seconds to 10 to provide a bit more leeway when large vehicles are slow to turn around the tight corners at the crossroads.
Result
The PC has addressed 3 significant issues in the village with this meeting.
The main change in the traffic light sequence to increase safety and reduce collisions will be actioned next year when NCC budgets allow. The PC has to determine the level of acceptable delay. In the meantime, the sequence will be delayed by 2 seconds to increase time each way as soon as possible.
The PC will submit photographic evidence of bad car parking.
The NCC traffic planners will try to find an improved layout to improve safety.
Our C. Cllr will continue to champion our request to ensure progression.
If any resident feels that they have a contribution to make, in the first instance please contact the clerk: –
clerk@ranskillparishcouncil.gov.uk
Alternatively, feel free to attend any Parish Council meeting, the timetable is on our website: –
www.ranskillparishcouncil.gov.uk
Ranskill Parish Council
October 2026
**Update**
Tthe clearance periods at the end of the green signals on both the Gt North Road stage and also the Blyth Rd/ Station Rd stage have been increased from the previous value of 8 seconds to 10 seconds. The change was made on Friday 23rd October. This should give an extra bit of breathing space for those vehicles waiting to turn right from the centre of the junction and delayed by slow moving vehicles turning around the 2 tight corners from Station Road and Blyth Road.
Birch Wood – Closure from 2nd November for about 2 weeks
/in News /by ClerkBirch Wood is owned by Nottinghamshire County Council.
The Parish Council has been lobbying for some time to clear fallen trees and open up this local resource.
A contractor has now been appointed by NCC. The wood and surrounding footpaths will be closed to the public from the 2nd November for up to two weeks.
Works to dead, dying and dangerous trees within falling distance of paths, Common Road, Access Road and Mattersey Road will be undertaken. There will be a significant amount of mainly birch, but also willow to be felled. The Forestry Commission is aware.
All felled material will be chipped or habitat stacked or left in the length to replicate natural processes within the woodland and provide a significant dead wood resource for invertebrates and other species.
We look forward to a refreshed wood becoming much more accessible.
Ranskill Parish Council
Ranskill – Illegal Waste Dump – Update Sep 2026
/in News /by ClerkFollowing intervention by our Member of Parliament, Jo White, the PC has received the attached letter from the Department for Environment, Food & Rural Affairs.
Great North Road Closure 17 – 28th August – 20.00 to 0500
/in News /by ClerkPlease find attached Roadworks Bulletin for (Preparation Patching for Surface Dressing) on:
A638 Great North Road Ranskill
A638 Great North Road Torworth
A638 Great North Road Barnby Moor
Surface Dressing Programme:
As Surface Dressing is a weather-dependent treatment, the programme remains subject to change throughout its delivery. The latest information and an explainer video about the programme can be found at www.nottshighways.co.uk/surfacedressing. Any changes to works dates are updated each working day.
Please find details below regarding each phased of surface dressing:
Preparation Patching for Surface Dressing
Deteriorated areas of the road surface will be patched and prepared, and any road studs are removed, to ensure the road surface is ready for surface dressing to be applied. These works will take place under a road closure at night in the majority of cases, minimising disruption to road users.
Surface Dressing Application
A bitumen emulsion and stone chips will be applied to the road surface. Works will take place under a road closure during the daytime – the road may be closed for a number of periods during the works, not the full duration. This process is weather dependent and as such the date of the work is subject to change.
Surface Dressing Encapsulation
A bitumen emulsion will be applied, ‘locking’ the stone chips and sealing the road surface. Works will take place under a road closure during the daytime – the road may be closed for a number of periods during the works, not the full duration. This process is weather dependent and as such the date of the work is subject to change.
Lining and Road Stud Installation – Post-Surface Dressing
Road lining and studs will be reinstalled following surface dressing, completing the process. These works will take place under a road closure at night in the majority of cases, minimising disruption to road users.
Senior Roadworks Coordinator (Bassetlaw)
Via East Midlands Ltd
Wildfires
/in News /by Clerk
WILDFIRE RISK – PLEASE TAKE CARE ON OUR PUBLIC RIGHTS OF WAY
With dry conditions increasing the risk of wildfires, the Rights of Way Team are asking everyone using local footpaths, bridleways and other public rights of way to take extra care.
Please:
• Stay on designated paths and follow any local warnings or restrictions.
• Do not light fires or use disposable barbecues.
• Never drop cigarettes, matches or other items that could start a fire.
• Take all rubbish home with you – including glass.
• Keep dogs under control and be mindful of livestock and wildlife.
• Please keep away from straw bales and do not climb on, move or damage them.
If you see smoke or a fire, move to a safe place and call 999. Do not attempt to tackle the fire yourself.
Parents & carers – please talk to children and young people about the consequences of deliberately starting fires. Setting fire to a straw bale or dry vegetation can have serious and potentially life-changing consequences. Wildfires can spread rapidly, particularly across dry grass, cropped fields and woodland. What may appear to be a harmless act or prank can quickly become a major emergency.
Your care and consideration can help protect our countryside, wildlife, local residents and emergency services.
Thank you for helping keep our local rights of way safe. 🙏
#WildfireSafety #StaySafe #PublicRightsOfWay #CountrysideCode #KeepItSafe
Ranskill – Illegal Waste Dump
/in News /by ClerkRanskill Parish Council has been contacted by a number of concerned residents following various media reports on illegal toxic waste dumping close to the village.
The Parish Council first reported suspicious activity around the site in May 2025 to both Bassetlaw District Council (planning enforcement) and Nottingham County Council. The matter was subsequently passed on to the Environment Agency. We are in regular contact with all appropriate authorities.
As this is an active ongoing police and EA investigation we are unable to provide further information as the issue is now out of our hands.
The matter is now being supervised by the Environmental Agency who are actively seeking residents who can provide witness statements to add to their case file. You can contact the Environmental Crime Officer as follows: –
Environmental Crime Officer | East Midlands Area Enforcement Team
Environment Agency | Trentside Offices, Scarrington Road, West Bridgford, Nottingham NG2 5FA
Customer Services 03708 506506
Incident Hotline 0800 807060
Ranskill Parish Council
Doncaster Sheffield Airport – Public Consultation
/in News /by ClerkDoncaster Sheffield Airport’s Airspace Change Proposal | Public Consultation
Today – Monday 3 August 2026 – Doncaster Sheffield Airport (DSA) has launched a public consultation about proposals to reinstate controlled airspace and introduce the arrival and departure procedures needed for DSA to reopen safely and bring passenger and cargo flights back to the region.
The consultation will run for 9 weeks from Monday 3 August – Sunday 4 October 2026, and we hope you can take part and share your views with us.
How to take part in this consultation
- We are holding a number of public consultation events and online webinars to support this consultation. I enclose our consultation leaflet which outline these events, please publicise this information as you wish to. Details of these events are also on our consultation website at the link below.
- Alternatively, you can view our consultation documents online on our consultation website – https://consultations.airspacechange.co.uk/doncaster-airport/dsa-airspace/3.
- Share your views with us: once you have reviewed the proposals and asked any questions you might have, please let us know what you think of the proposed changes via the online questionnaire on the consultation portal: https://consultations.airspacechange.co.uk/doncaster-airport/dsa-airspace/
Further information
If you have any questions or require further information that is not detailed within the attached leaflet, please do not hesitate to get in touch with our consultation team at dsa-airspaceconsultation@flydsa.com or on 0800 043 3099.
Yours sincerely,
Doncaster Sheffield Airport Airspace Change Team
Electoral Register
/in News /by ClerkResidents may receive a text, email or letter from Bassetlaw District Council. If they are contacted, they should check that the details on the register for their household are correct and provide updated information if necessary.
If our Electoral Services Team have an email address residents should have received an email from elections@bassetlaw.gov.uk around 27th July 2026, this is a genuine email and responding means that we will not need to send a letter in the post. If we don’t hold an email address, we will have sent a letter to the property around the same time.